White Otter Falls
Location Kapuskasing, On
Installed Capacity 5.5 MW
Generating Flow 40 m³/s per turbine
Total Investment 29 millions $
Annual Production 21,106 MWh
Construction 25 months
Commissioning Summer 2013
Project White Otter Falls
The main characteristics of the facility are :
- The powerhouse, intake (50 m) and tailrace canal (75m) are located on the left bank of the river.
- The overflow weir is 120 m in length, and is comprised of two 45-m long rubber dams. The concrete base of the weir varies from 0,5 to 1 m in height, and is topped with a 2.0-m diameter rubber dam.
- An approximately 6.5 km long head pond that covers an additional surface area of 23 ha. Normal operating level is 241.20 m.
- The powerhouse is equipped with two S-Shape turbines, each with a capacity of 2.75 MW.