General Presentation
Flow measurements on the canal near the locks have demonstrated to the St-Lawrence Seaway Authority that Côte Ste-Catherine I caused no disturbances to navigation. Consent was granted for the construction of the second phase of
this project.
The commissioning of Côte Ste-Catherine II occurred on December 1, 1993. The new installation was built next to Côte Ste-Catherine I taking advantage of the same 12 meter head. Phase II benefits from a substantially higher capacity
(4.8 MW) and uses the same siphon method concept successfully implemented in Phase I.
 |
 |
|
Gross head : 12 m
|
|
Rated flow : 54 m3/s
|
|
3 Kaplan turbines : 1 600 kW
|
|
Runners diameter : 1800 mm
|
|
Capacity : 4 800 kW
|
|
Annual production : 37 350 000 kWh
|
|
|
|
Duration of construction : 16 months
|
|
Commissioning : December 1993
|
| Total investment : 10 million dollars |
|
 |
 |
Note: The Côte Ste-Catherine II hydroelectric facility is not the property of
Hydromega services inc anymore.